Kauaʻi – Construction is set to begin tomorrow at the Kikiaola Small Boat Harbor on various site improvements. These improvements include installation of a new water main, installation of a new prefabricated comfort station with an individual wastewater system, resurface asphalt pavement, new concrete pavement at boat ramp approach, new boat ramp concrete panels, relocation of the boat wash down area and drainage upgrades.
Various portions of the harbor will be closed at various stages of the project including closure of the boat ramp; however, there will be no extended closures that will interrupt normal harbor operations.
Cushnie Construction Company, Inc. is the contractor, and the construction cost will be $1,942,296 with an estimated completion in late September 2021.
Kikiaola Small Boat Harbor is located two miles west of the Waimea River mouth on Kaua’i with 4 moorings for vessels of draft less than 3 feet, a boat ramp, vessel wash down, loading dock and restrooms.